Patapsco Regional Greenway -- Comments requested

31a266dd-e177-4367-97df-99caa0738709.png

The Baltimore Regional Transportation Board (BRTB), as the metropolitan planning organization for the Baltimore region, seeks public comments through Friday, July 17 on a new section of the Patapsco Regional Greenway in Howard and Baltimore Counties

In 2017, the BRTB approved a concept plan for the Patapsco Regional Greenway. Now they are seeking your input on the Elkridge to Guinness route.

Choosing the Best Pathway

Earlier this year, the design team studied the area and developed three options, also called “alignment alternatives,” for the Elkridge to Guinness connection and the Patapsco River crossing.

Each of the three potential trail placements include a Patapsco River crossing. All alternatives would also pass through the numerous wetlands and floodplains of the Patapsco River Valley. Federal and State regulations provide protections for the river and its associated wetlands and floodplains, so the design team looked for options that would minimize impacts to these environmental resources.

The BRTB seeks feedback on three possible trail routes. Highlights are below.

Alternative 1: The Patapsco Route

The Patapsco Route has several options to take trail users through the floodplain of the Patapsco River and into Historic Elkridge via a bridge over the Patapsco River. Changing Main Street in Elkridge to a one-way road would provide enough space for a low-stress separated bike lane.

Length: Cost Range:

1.8 Miles $2.5 to $4.2 Million

c5589620-d421-4471-85e8-e6bc3a4cc7d7.jpg

Alternative 2: The Northern Link

The Northern Link efficiently ties the area of Guinness Open Gate Brewery to the Thomas Viaduct inside the Patapsco Valley State Park. Sharrows, also known as shared lane markings, along the low-volume Levering Avenue would allow trail users to come into Historic Elkridge.

Length: Cost Range:

1.2 Miles $1.9 to $2.4 Million

08ac750f-0580-4454-840e-7bcc766544e5.jpg

Alternative 3:  Elkridge Spur

The Elkridge Spur provides efficient connections between the Guinness Open Gate Brewery, Historic Elkridge and the Park, with an optional loop trail that would also provide an opportunity to enjoy the serenity of the Patapsco River.

Length: Cost Range:

2.5 Miles $3.8 to $4.3 Million

e2327cb6-fcf2-4b73-830c-1978f3dd8aa0.jpg

Based on your input, and the input of our project partners, the project team will choose a preferred alignment and complete a preliminary design. Once 30% design is completed, Howard and Baltimore Counties will apply for a grant to complete the design.